Project Review


Vanessa Valderrama
 

I'd like to propose the TSC review these inactive projects to determine if they can be archived.

Projects that have been inactive for 18 months or longer

  • Project: ONE
    • Last commit: Tue Oct 31 15:49:06 2017 +0000
  • Project: NSH_SFC
    • Last commit: Sat Jun 2 02:23:05 2018 +0800
    • Comment: All the code in NSH_SFC has been merged into VPP master branch
  • Project: PUPPET-FDIO
    • Last commit: Tue Jan 30 14:35:45 2018 +0100
    • Comment: The project is not active but may still be consumed by tripleo project in openstack
  • Project: RPM_DPDK
    • Last commit: Thu Jul 5 13:14:14 2018 -0400
    • Comment: The project is not active. PTL recommends project termination
Projects that were never active (empty repositories)
  • Project: ODP4VPP
    • Initial commit: Tue Jan 31 20:11:51 2017 +0000
  • Project: P4VPP
    • Initial commit: Fri Aug 25 17:17:23 2017 +0000
Thank you,
Vanessa